UHPC Wear protection for an ore pallet plant in Bahrain

We have an order to supply and install a UHPC wear protection liner in a new grinding system at an ore processing plant in Bahrain. The new grinding system was designed and delivered by a large German plant manufacturer.

UHPC wear protection was specified by this plant manufacturer as wear protection for his system.

The contract included the lining of pipelines, cyclones and separator systems. The assembly of a 25 mm / 1 inch UHPC wear protection liner with a total area of over 600 sq / 6450 sq ft was performed by a local installation company under the supervision of one of our supervisors.

24 hours after the individual plant elements were lined, they could be mounted in the ore processing plant.